Happy family

Find a legal form in minutes

Browse US Legal Forms’ largest database of 85k state and industry-specific legal forms.

29 USCS § 2102

The Warn Act can be found in 29 USCS § 2102 and it reads as follows:

 “§ 2102 Notice is required before plant closings and mass layoffs
(a) Notice to employees, state dislocated worker units, and local governments. An employer shall not order a plant closing or mass layoff until the end of a 60-day period after the employer serves written notice of such an order–

 (1) to each representative of the affected employees as of the time of the notice or, if there is no such representative at that time, to each affected employee; and

 (2) to the State or entity designated by the State to carry out rapid response activities under section 134(a)(2)(A) of the Workforce Investment Act of 1998 [29 USCS § 2864(a)(2)(A)], and the chief elected official of the unit of local government within which such closing or layoff is to occur.

If there is more than one such unit, the unit of local government which the employer shall notify is the unit of local government to which the employer pays the highest taxes for the year preceding the year for which the determination is made.
(b) Reduction of notification period.

(1) An employer may order the shutdown of a single site of employment before the conclusion of the 60-day period if as of the time that notice would have been required the employer was actively seeking capital or business which, if obtained, would have enabled the employer to avoid or postpone the shutdown and the employer reasonably and in good faith believed that giving the notice required would have precluded the employer from obtaining the needed capital or business.

(2) (A) An employer may order a plant closing or mass layoff before the conclusion of the 60-day period if the closing or mass layoff is caused by business circumstances that were not reasonably foreseeable as of the time that notice would have been required.

(B) No notice under this Act [29 USCS §§ 2101 et seq.] shall be required if the plant closing or mass layoff is due to any form of natural disaster, such as a flood, earthquake, or the drought currently ravaging the farmlands of the United States.

(3) An employer relying on this subsection shall give as much notice as is practicable and at that time shall give a brief statement of the basis for reducing the notification period.

(c) Extension of layoff period. A layoff of more than 6 months which, at its outset, was announced to be a layoff of 6 months or less, shall be treated as an employment loss under this Act [29 USCS §§ 2101 et seq.] unless–

(1) the extension beyond 6 months is caused by business circumstances (including unforeseeable changes in price or cost) not reasonably foreseeable at the time of the initial layoff; and

(2) notice is given at the time it becomes reasonably foreseeable that the extension beyond 6 months will be required.

(d) Determinations with respect to employment loss. For purposes of this section, in determining whether a plant closing or mass layoff has occurred or will occur, employment losses for 2 or more groups at a single site of employment, each of which is less than the minimum number of employees specified in section 2(a)(2) or (3) [29 USCS § 2101(a)(2) or (3)] but which in the aggregate exceed that minimum number, and which occur within any 90-day period shall be considered to be a plant closing or mass layoff unless the employer demonstrates that the employment losses are the result of separate and distinct actions and causes and are not an attempt by the employer to evade the requirements of this Act [29 USCS §§ 2101 et seq.]. 

If there is more than one such unit, the unit of local government which the employer shall notify is the unit of local government to which the employer pays the highest taxes for the year preceding the year for which the determination is made.


Inside 29 USCS § 2102